Conversion Schemes

Conversion Schemes

Material Change of  Use is required under Building Regulations if you are proposing to carry out a barn conversion or forming flats/dwellings from an existing building.

Material Change of Use schemes need to comply with Approved Document L.

SAP Calculations are requried for conversion schemes, however, the requirements are not as stringent as new dwelling SAP Calculations.

They need to comply with Part L for U-Values, heating systems etc.

For conversions it is possible to offset certain elements for example some clients like to have an existing exposed stone wall for feature purposes.

We can carry out these tradeoff calculations however Building Control should confirm they are happy with this approach.

Please see FAQ Below for further information.

Get In Touch

    Frequently Asked Questions

    What information do I need to provide?

    For a full and accurate SAP Assessment you will need to provide the following;

    • Location Plan
    • Floor Plans
    • Elevations
    • Sections (a section is required for each variation of the proposed dwelling).
    • Technical Specification (This will be indicative and RTS will amend and design specifications in order to achieve compliance).
    Current U-Values - New Thermal Elements
    Element typeMaximum U-value(1) W/(m2·K)
    Roof0.15
    Wall0.18
    Floor0.18
    Swimming pool basin0.25
    Window1.4 or Window Energy Rating(10) Band B minimum
    Rooflight2.2
    Doors with >60% of internal face glazed1.4 or Doorset Energy Rating(10) Band C minimum
    Other doors1.4 or Doorset Energy Rating(10) Band B minimum
    Current U-values - Existing Thermal Elements
    (a) U-value Threshold(b) U-value Improved
    Roof: 0.350.16
    Wall - cavity insulation: 0.70.55
    Wall - internal or external insulation: 0.70.3
    Floor: 0.70.25

    If existing thermal elements achieve a U-value equal to or lower than threshold (a) then no upgrading will be required, however, if the U-valiue is above threshold A then the element will need to be improved to the U-value in column (b).